Project Title: 2003 Substation Expansion Project
Completion Date: December 29, 2003
Project Duration: 3 Months
Design, engineering, construction and commissioning of a 2.5 MVA
substation required for plant expansion (Turn-key Project).
Equipment utilized as part of the design included S&C Electric, Carte,
and Square D.